RE: Virgin Trains
Its more to do with the fact that there is no chance in hell that DOR can be legally ready in time for Dec 9th. It was always touch and go while they were piggy-backing on the First mobilisation - ie. exactly the same strategy and documents apart from the names etc. 120 days for mobilisation was quoted, they started around 85/90.... Plus DOR still hadn't even applied to ORR for a Safety Case. |
||||||